Complaint ID 113641 — Public Copy
Report generated October 17, 2026 1:36 PM.
On this Page
Status: Approved/Closed
- Complaint Received
- August 13, 2025 9:15 AM
- Assigned Office
- Mountain District
- Complaint Closed
- March 14, 2026 1:26 PM
- Review Comments
- [Not entered]
Nature of Complaint
On 8/13/25, EPD Director Jeff Cown received the following letter: "I am writing to you as a concerned resident of the Clearwater neighborhood of Lake Arrowhead, situated within Cherokee County, Georgia, to formally lodge a complaint regarding stormwater runoff into streams and into Lake Arrowhead. The project is named Lake Arrowhead Phase 2 Unit 12 according to the permits issued by Cherokee County , and it encompasses almost 99 acres, with 42.46 disturbed acres. Since the fall of 2024, residents have observed ongoing consequences from stormwater discharge, which have impacted both our properties and the Lake itself. Stormwater runoff from the impacted area flows into Shut-In Creek and unnamed tributaries, then into Lake Arrowhead which discharges into a tributary of Lost Town Creek, all of which are part of the Etowah River Basin. Cherokee County has issued two separate Stop Work Orders to the developer for failure to contain sediment on site and out of the stream buffer, which we appreciate. However, within days of lifting the first Stop Work Order, we observed high turbidity into the coves once again. The second Order which was in place for a very short period of time, was just lifted last week as a result of a promise from the developer to complete a retaining wall. The developer claims to have low sampling results for turbidity following rainfall, but the samples were taken the day AFTER the rainfall events, even when the rainfall occurred during daytime working hours. This appears to directly violate the terms of Georgia EPD’s NPDES General Permit to discharge storm water associated with construction activity. As I read the conditions of the General Permit, turbidity sampling is required within 45 minutes from the beginning of a rainfall event, or as soon as possible. However, for example, on July 21, 2025, we received 0.9 inches of rainfall from around noon until 2:00 pm. According to Cherokee County, the developer’s third-party contractor waited until mid-morning on July 22, 2025, to sample for turbidity and of course the outfall was quite clear in appearance by then. Yet these results are being touted as evidence of the “successful” implementation of the developer’s best management practices. There are other concerns, including noticeably less sitings of fish and turtles in the coves this summer, but hopefully the above information is enough to provide a clear picture of the issues occurring here. The Cherokee County Engineering Department’s efforts to try to regulate this large and complex development are appreciated. However, it appears that the developer has little fear of escalated enforcement beyond brief stop work orders. I firmly believe that all parties would benefit from an additional review by your agency which is tasked with the protection and stewardship of Georgia's vital water resources. My wife and I, along with other nearby residents have photographed the ongoing problems. Attached are a small set to provide a visual indication of the effects of the high turbidity levels which have been allowed to flow into two separate coves within the Clearwater neighborhood as well as the very hilly and steep topography of the project. My request is that Georgia EPD conduct an unannounced site visit and a thorough file review of this ongoing project. Our concerns grow each day that heavy rainfall is predicted. If you need additional information, please contact me. Thank you for your attention to this issue, and for all that you do to protect our environment."
- Primary Concern
- Erosion & Sedimentation Control
- Secondary Concern
- [Not entered]
Complaint Location
- Location of Complaint
- Lake Arrowhead
- City of Complaint
- Waleska
- County of Complaint
- Cherokee County
Source
- Source Name
- Lake Arrowhead Phase 2 Unit 12
- Facility ID Number
- GAR395A39
Source Contact
- Contact Name
- Matthew Wilkes
- Source Address
- 201 Stafford Lane
Villa Rica, Georgia 30180
Actions
Enforcement conference
4‑Mar‑2026 by Rebecca Fulle
Other
27‑Feb‑2026 by Rebecca Fulle
Other
16‑Feb‑2026 by Rebecca Fulle
Follow-Up Investigation
12‑Jan‑2026 by Rebecca Fulle
Referred To
12‑Jan‑2026 by Rebecca Fulle
Other
5‑Jan‑2026 by Rebecca Fulle
Other
26‑Nov‑2025 by Rebecca Fulle
Follow-Up Investigation
9‑Oct‑2025 by Jonathan Wells
Other
7‑Oct‑2025 by Jonathan Wells
Follow-Up Investigation
18‑Sep‑2025 by Jonathan Wells
Follow-Up Investigation
17‑Sep‑2025 by Jonathan Wells
Other
17‑Sep‑2025 by Jonathan Wells
Other
16‑Sep‑2025 by Jonathan Wells
Other
8‑Sep‑2025 by Jonathan Wells
Other
2‑Sep‑2025 by Jonathan Wells
Other
22‑Aug‑2025 by Jonathan Wells
Other
22‑Aug‑2025 by Jonathan Wells
Other
21‑Aug‑2025 by Jonathan Wells
Initial Investigation
20‑Aug‑2025 by Rebecca Fulle
Other
15‑Aug‑2025 by Rebecca Fulle
Attachments
(Attachments may not be available for complaints resolved before April 2018. Please note that not every complaint has attachments.)